Maintenance Shutdown Schedule

 

The augmentation and maintenance work will be carried out in the areas mentioned below to ensure an uninterrupted power supply and no equipment failure / breakdown.

Due to this, the Electricity supply may be affected in the following areas on

 

Thursday, August 21, 2014.

S. No

District

Zone

DESCRIPTION

Time from

Time to

Area affected

Total Duration (in Hrs)

Consumer

1

BADLI

516

PREDECTIVE MAINTENANCE

11:00 AM

1:00 PM

PART OF SHAHBAD

2:00 Hrs

300

2

BADLI

507

PREDECTIVE MAINTENANCE

8:30 AM

10:30 AM

GALI NO. 8 HVDS AND GALI NO. 9 RIGHT SIDE

2:00 Hrs

150

3

BADLI

507

PREDECTIVE MAINTENANCE

11:30 AM

1:30 PM

GURU DWARA ROAD HVDS

2:00 Hrs

150

4

CIVIL LINES

416

PREDECTIVE MAINTENANCE

10:30 AM

1:30 PM

GURMANDI,RAJPURA AND KHATIK BASTI

3:00 Hrs

370

5

CIVIL LINES

416

PROJECT WORK

11:00 AM

4:00 PM

PART OF HUDSON LINE

5:00 Hrs

210

6

KESHAV PURAM

502

PROJECT WORK

11:00 AM

5:00 PM

F BLOCK AND E BLCOK JJ COLONY

6:00 Hrs

200

7

MANGOLPURI

515

PREDECTIVE MAINTENANCE

10:00 AM

1:00 PM

PART OF F BLK

3:00 Hrs

500

8

MANGOLPURI

515

PREDECTIVE MAINTENANCE

2:00 PM

5:00 PM

PART OF F-2 BLK

3:00 Hrs

500

9

MANGOLPURI

519

PROJECT WORK

11:00 AM

3:00 PM

RAJIV NAGAR HVDS

4:00 Hrs

750

10

MODEL TOWN

415

PREDECTIVE MAINTENANCE

12:00 PM

1:30 PM

ADARSH  NAGAR EXTN , MOTI  LAL  ROAD , NEHRU ROAD ,     RAJAN   BABU  ROAD

1:30 Hrs

350

11

NARELA

517

PROJECT WORK

12:00 PM

2:00 PM

PART OF PALLA AGRICULTURE AREA

2:00 Hrs

300

12

ROHINI

561

PREDECTIVE MAINTENANCE

10:30 AM

12:00 PM

B-9, B8,B7 SEC5 ROHINI

1:30 Hrs

300

13

ROHINI

561

PREDECTIVE MAINTENANCE

2:00 PM

4:00 PM

PART OF D-6, D-7, C-5, D6 MARKET SEC6 ROHINI

2:00 Hrs

300

14

ROHINI

561

PREDECTIVE MAINTENANCE

12:00 PM

1:30 PM

B-9, B8,B7 SEC5 ROHINI

1:30 Hrs

300

15

SHALIMAR BAGH

503

PROJECT WORK

11:00 AM

6:00 PM

BHALSWA DAIRY B &C BLK

7:00 Hrs

350

16

SHALIMAR BAGH

532

PROJECT WORK

10:00 AM

6:00 PM

HARIJAN BASTI, SURENDER COLONY PART-1,2,3 , JHARODA VILLAGE, SHIV KUNJ

8:00 Hrs

5000

 